One of the good things about software is that people seem to want
it, and want it quickly. It's usual for organizations to ask teams
to speed up production of software and from time to time the
organization seeks to help in the way that really shows its
commitment - by spending money to add more people to the team.
Now there's many an argument that's been had as the true benefit
of adding people to a software team. It's clear to me that you don't
get a linear benefit, doubling a team won't double its productivity
because the communication and coordination costs kick in and blunt
the increase. My utterly unscientific rule of thumb is that any
increase in productivity is likely to be proportional to the square
root of the increase in people, so doubling a team will get you
roughly a 50% increase in productivity. But in practice this will
vary a great deal depending on individual factors. There are some
people I know who are likely to double the productivity of even a
sizable team just on their own, and we have run into people who will
reduce a team's productivity.
But the issue I want to highlight here is that of the ramp-up.
You have a small team that's working well, but you want more
software and you are prepared to spend the money to get it. You're
happy to pay quadruple, even sextuple to double your rate of
progress. An important, yet not well understood factor is the rate
at which you can safely add people to a team.
More than once, I've come across projects who added too many
people too quickly. This manifests itself in a breakdown of the
cohesion of the code base itself. Duplication runs rampant, several
friends of mine know about the project that had three
object-relational mapping frameworks within a single application.
This breakdown occurs because the new people don't understand
how the code base currently works, so they do something at odds with
it, like adding a competing framework. If there's too many new
people around, the team leadership can't keep track of it all and
the code base sprouts problems. These problems then reinforce each
other because nobody can find a consistent way to do things, the
Broken Windows syndrome kicks in and you get a positive feedback
loop. (And positive feedback loops are usually a bad thing.)
On top of this an overly rapid ramp up leads to a break down of
the human communication mechanisms. It takes time for people to get
used to working with each other and a rapid ramp up can stop a
large team from forming the relationships it needs to succeed.
So how much ramp up can you safely do? It's difficult to give any
concrete advice here, because any experienced project manager I ask
always rightly points out that there are many variables that have to
be taken into account. I pressed Joe Zenevitch, one of my most
trusted PM sources, and he indicated that he would never want to
more than double a team at once. Even doubling would be a risky
call, with the risk increasing if the exisiting team was already a
dozen or more people, or had a signficant amount of juniors.
If you do a significant increase in size you shouldn't add yet
more people until the new folks have settled into the team. It will
take a few weeks for this to happen. Developers need to get to know
the code-base and the domain, BAs need to be familiar with the
domain experts, everyone needs to get to know each other. At
ThoughtWorks we expect people to come up to speed quickly, after all
we hire bright, high motivated people who are quick learners. But
even so it still take a week or two. For most teams you should allow
a good bit longer.
When you add people to a team, you don't get an immediate
increase in capability. It takes time for people to become
productive on a new project. Worse still existing staff have to
spend time helping them get up to speed, so your velocity may well drop at first. Joe Z's
observation for ThoughtWorks teams is that there will be no net
effect for the first couple of weeks as the new people and hit for
existing people cancel out. [1] Most
ThoughtWorkers like to point out that pair programming is a big
enabler to on-boarding people more rapidly. Pat Kua also has some good
advice on how to bring new people onto a team effectively.
Another thing to watch is to not ramp-up too early in the
project. One of the firmest bits of advice I've heard from people
who do large projects (anything over 50 people) is that the project
should start small, maybe with just a dozen or so developers. They
should figure out the key design elements and interactions of the
system by building early parts of it. Only once that design has
settled down should you think of increasing the team size to its
full size. As part of that settling down put time into
removing any design elements that you don't think should be copied.
People will naturally copy stuff that's already there, so you should
ensure that what's there is all going to make a good platform for
further development. This is a time to err on the side of excessive
attention to code-cleanliness.
Finally, when thinking of ramping up, think very carefully about
whether it's worth it. I've rarely come across a large team where
there isn't a feeling that the team could be significantly cut
without reducing its productivity. As I once said "scaling
agile is the last thing you want to do".
1:
This couple-of-weeks rule is for ThoughtWorkers, so we would
expect it would take longer for people who don't match our
hiring standards.